In England and Wales you must give your neighbour written notice between 2 months and a year before starting work on a party wall, on the boundary or digging near their foundations. They have 14 days to consent in writing; silence or refusal starts the dispute process and a party wall award by surveyors, according to GOV.UK.
What counts as a party wall
| Party wall | A wall standing on the land of 2 or more owners, either part of a building or a separate wall such as a garden wall. Wooden fences do not count.1 |
| Party structure | A floor or other structure separating parts of a building with different owners, for example between flats.1 |
| Separate from planning | A party wall agreement is different from planning permission and building regulations approval. Scotland has different rules.1 |
Work that needs notice
| Boundary work | Building on or at the boundary between the 2 properties.1 |
| Existing wall | Work on an existing party wall or structure: cutting into it, raising, lowering or deepening it, removing chimneys, or knocking it down and rebuilding.1 |
| Excavation | Digging below and near the foundation level of the neighbour's property.1 |
| No notice needed | Minor work such as plastering, replacing wiring or sockets, or drilling to put up shelves or cabinets.1 |
Timeline and agreement
| Serving notice | In writing, between 2 months and a year before work starts, saying what you plan to do.1 |
| Neighbour's reply | Written consent within 14 days. No reply does not mean agreement: it starts the dispute process.1 |
| Counter notice | The neighbour can ask for extra work within a month of the first notice, and pays for it if it benefits them.1 |
| Surveyors | If you cannot agree, one surveyor is appointed jointly or each side appoints its own. You cannot be your own surveyor.1 |
| Party wall award | A legal document setting out the work, how and when it is done, and who pays, including surveyor fees.1 |
| Appeal | To a county court within 14 days of receiving the award.1 |
| Access | The neighbour must allow access in usual working hours on 14 days' notice, except in an emergency.1 |
Who pays
| Building owner | Pays for the work they start on a party wall, and must fix or pay for any damage caused.1 |
| Neighbour | May share costs where work is needed because of defects or lack of repair, or for extra work they ask for.1 |
General information from official sources, not legal, tax or immigration advice. Rules change; check the source and take advice from a qualified professional before buying or moving.
Frequently asked questions
How much notice must I give for party wall work?
Between 2 months and a year before the work starts, in writing.
Can my neighbour stop my building work?
No. Neighbours cannot stop lawful work, but they can affect how and when it is carried out.
What happens if my neighbour does not reply?
No reply within 14 days counts as a dispute, and surveyors must be appointed.
Who pays the party wall surveyor?
The party wall award sets out who pays, including surveyor fees. The owner starting the work pays for that work.
Do I need a party wall agreement for a loft conversion?
You must give notice if the work cuts into, raises or otherwise alters a party wall.